Chapter 2: Meter Installation

Chapter 2: Meter Installation
The StorEdge solution requires connecting a meter   f or   S mart Energy Management applications, such as 
export limitation and maximizing self-consumption.
The meter type (single or three phase) and number of current transformers (CTs) should be selected per 
the grid connection and energy management application rather than according to the inverter model. 
The   C Ts are supplied with 2m twisted pair wires for connecting the CTs.
To install the SolarEdge meter, refer to the installation guide supplied with it: 
http://www.solaredge.com/files/pdfs/solaredge-meter-installation-guide.pdf.
The meter is connected to the inverter using RS485.                
RS485 wiring specifications:
 
Cable type: Min. 3-wire shielded twisted pair (a shielded Ethernet cable (Cat5/5E STP) 
l
may be used)
 
Wire cross-section area: 0.2-1 mm²/ 24-18 AWG (a CAT5 cable may be used)
l
NOTE
The inverter RS485 bus should be connected to the battery (via the StorEdge
interface) and meter. Connecting multiple inverters (or an external logger) with
RS485 master-slave connection may require an RS485 Expansion Kit (available
form SolarEdge; Refer to
kit_installation_guide.pdf).
To connect the meter to the inverter:
 1.  Remove the seal from one of the openings in communication gland at the bottom of the inverter and 
insert the RS485 wires from the meter through the opening.
 2.  Pull out the   R S485 connector located on the communication board.
8
http://www.solaredge.com/files/pdfs/RS485_expansion_
    
Figure 3: Communication glands
     
Figure 4: Inverter RS485 connector