Presto Conti Compact Series Operating And Maintenance Instructions Manual page 68

Channel-type baling press
Table of Contents

Advertisement

PRESTO
GmbH & Co. KG
Bad Laer
Check condition and tight fit of hydraulic lines
and screwing
Put main switch into "0" position
and secure with a padlock before
you start with this work.
• Check all pipe and hose connections for
tight fit. Retighten if required. This check
has to be carried out for the first time
approximately 4 weeks after the
commissioning of the unit. All further
controls have to be carried out according
to the interval stated in the maintenance
schedule.
• Carry out a visual inspection for obvious
damages on this occasion. Keep an eye
on fabric damages at hoses, damages at
pipes etc.
04/2012
7 - 14

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Conti Compact Series and is the answer not in the manual?

Table of Contents