Check condition and tight fit of hydraulic lines
and screwing
Put main switch into "0" position
and secure with a padlock before
you start with this work.
• Check all pipe and hose connections for
tight fit. Retighten if required. This check
has to be carried out for the first time
approximately 4 weeks after the
commissioning of the unit. All further
controls have to be carried out according
to the interval stated in the maintenance
schedule.
• Carry out a visual inspection for obvious
damages on this occasion. Keep an eye
on fabric damages at hoses, damages at
pipes etc.