CONNECTING THE MANUAL GUN

Designation
1 Powder cup gun
2 Electrical connection cable
3 Control unit
4 Dosing air hose (blue)
5 Feed air hose (red)
6 Atomizing air hose (black)
7 Use non-return valve with feed
and dosing air!
Procedure:
1. Switch off the high-voltage
generation on the control unit.
2. Before connecting the cup gun,
check that all components, such as
the nozzle system and union nut,
are correctly fitted.
3. Connect electrical cable of the cup
gun to the control unit.
4. Connect the feed air hose to the
cup gun and to the control unit.
5. Connect the dosing air hose to the
cup gun and to the control unit.
6. Connect the atomizing air hose
to the cup gun and to the control
unit.
6.6

GROUNDING

For safety reasons, the control unit must be properly grounded. The grounding connection
to the energy supply (socket) takes the form of the mains connection cable's protective
conductor, while that to the work piece/system is via the knurled screw on the rear of the
control unit. Both connections are absolutely essential. If installed correctly as described
above, the spray gun is grounded via the gun cable between the control unit and spray gun.
Good grounding of the work piece is also necessary for optimum powder coating.
A poorly grounded work piece causes:
– dangerous electric charging of the work piece
– very poor wrap-around
– uneven coating
– back spraying to the spray gun, i.e., contamination