© Martin Engineering GmbH
Diameter of the drum* in mm
400
>=400
*incl. Friction material and conveyor belt
Tab. 2: X values for the positioning of the mainframe
5. Add measurement X from table 2 to measurement A.
6. On the chute wall, mark a circular arc around the midpoint with
the measurement determined in step 5 (1, Fig. 1).
Fig. 2: Marking the installation height
WARNING! DANGER OF INJURY!
The primary cleaner is heavy and can cause serious injury if it falls
when being lifted or moved.
Only lift the primary cleaner using suitable lifting equipment or with
several persons. Do not stand under suspended loads.
7. Mark a horizontal line below the horizontal centre line of the
head drum at a distance of 216 mm. The intersection with the
arc marked in step 5 is the midpoint of the mainframe (3, Fig. 2).
90°
3
min.
216
mm
16
Measurement X in
mm
102
89
90°
M3618UK-11/14