1. Before starting with the work of installing the conveyor belt sys-
tem, switch off all accessories and secure them against being
switched on again inadvertently.
NOTE
The MARTIN
®
QC
#1 heavy-duty pre-cleaner is only installed in
the front lower quarter of a head drum. The specified installation
measurements must be strictly observed.
2. Determine the midpoint position of the mainframe as described
below for the primary cleaner.
Fig. 1: Marking the installation radius
NOTE
Martin Engineering recommends the installation of a MARTIN
inspection door for improved maintenance and repair access.
3. Mark the vertical and horizontal centre line of the driving drum
to determine the midpoint (1, Fig, 1) of the driving drum. The
vertical line must run at right angles to the conveyor line.
4. Determine or measure the radius (measurement A) of the driv-
ing drum including the thickness of the covering and the con-
veyor belt.
A + X
1
15
®
M3618UK-11/14