(CC100Ps) and liquid-side stepper valve case con-
trollers (CC100LSs) in this field.
Suction Controllers (CC100H) Enter the num-
ber of suction stepper case controllers (CC100Hs) in
this field.
Circuit Suction (CS100) Enter the number of suc-
tion lineup circuit controllers (CS100s) in this field.
ESR8 Line Up Boards Enter the number of ESR
suction lineup circuit boards (SR100s) in this field.
TD3 Temperature Displays Enter the number of
TD3 temperature display units in this field.
EC2- 29x Case Controllers Enter the number of
EC2-29x refrigerated case controllers in this field.
EC2-39x Case Controllers Enter the number of
EC2-39x refrigerated case controllers in this field.
Echelon 16AI Enter the number of 16AIe analog
input boards in this field.
Echelon 8RO Enter the number of 8ROe analog
input boards in this field.
3.7.2

Commissioning a Device

Once all records have been created and defined for all
devices on the Echelon Network, they must be "commis-
sioned." Commissioning is necessary for the E2 to identify
and establish communications with all devices on the net-
work.
To start commissioning, open the Network Summary
screen:
1.
Press
to open the Main Menu.
2.
Press
(System Configuration).
3.
Press
(Network Setup).
4.
Press
(Network Summary).
16
E2 RX/BX/CX I&O Manual
Figure 3-13
- Network Summary Screen
NOTE: A device may only be commissioned if
it is properly connected on the network and
powered up.
How Echelon Commissioning Works
Each device that is capable of communicating on a
Echelon Network has a unique 12-digit "Neuron ID" code
number that is hard-coded in a chip on the board. In order
for the E2 to begin communications with a unit controller
or another E2, it must know the device's ID number.
When a device is commissioned, its 12-digit code is
either entered by hand into the E2 (via the front panel key-
board) or sent across the network to the E2 using the
device's service button. Once the E2 knows the device's
12-digit ID, it establishes communication and gives the
device its user-defined subnet and node address. From that
point on, the E2 uses only the subnet and node address to
communicate with the device.
As mentioned above, there are two ways in which a
device may be commissioned. No one way is better than
the other in terms of effectiveness, but one of the methods
may be less difficult than the other depending on the type
of installation.
MODBUS Commissioning
If commissioning a MODBUS device and multiple
MODBUS ports are available, you will be prompted to
select the appropriate network during the commissioning
process.