Prepare boiler location
Placing multiple boilers
1. Locate multiple boilers in boiler room to
provide the clearances shown in:
a. Figure 3 (side-to-side), or
b. Other layouts can be used if all re-
quired clearances are maintained.
2. Provide indicated clearances around
boilers for access and servicing. If rec-
ommended dimensions are not possible,
Figure 3
Side-to-side mounting of multiple boiler
8
(continued)
provide at least the minimum clearances
given on page 7 . Also follow local codes.
3. Construct boiler foundation if boiler
room fl oor is uneven or if there is a danger
of fl ooding. Size foundation to allow for
clearance and spacing dimensions shown
in either Figure 3 .
Verify that boiler placement and clearances
comply with all applicable codes.
4. Chalk-line boiler locations on foundation
or boiler room fl oor.
5. Uncrate and assemble boilers according
to instructions in this manual.
6. Provide clearance for installation of vent-
ing, air piping, gas piping, condensate
piping and components, expansion tank,
boiler pump and other accessories.