Commercial Condensing Gas-Fired Water Boiler — Boiler Manual
DIRECT EXHAUST — Boiler room air openings
Figure 26
MINIMUM combustion air openings for direct exhaust applications —
Air openings
The required air opening sizes below are FREE AREA,
after reduction for louver obstruction. Note the exception
below for large spaces.
ing option.
Part number 550-100-250/0819
TM
SVF
boiler
WITH other
appliances in room
TWO
openings, each at least:
1
1,000
square inch per
of all appliances in the room,
but not less than 100 in
TWO
openings, each at least:
1
2,000
square inch per
of all appliances in the room
— OR —
ONE
opening **, each at least:
1
3,000
square inch per
of all appliances in the room
TWO
openings, each at least:
1
4,000
square inch per
of all appliances in the room
— OR —
ONE
opening **, each at least:
1
3,000
square inch per
of all appliances in the room
TWO
openings, each at least:
1
2,000
square inch per
of all appliances in the room
— OR —
ONE
opening **, each at least:
1
3,000
square inch per
of all appliances in the room
A single combustion air opening can be used for cases b, c or d above, sized as listed,
provided that:
The single opening must communicate directly to the outdoors or to a space that
-
communicates directly with outdoors (NOT to an interior space).
The top of the opening must be within 12 inches of the ceiling.
The free area of the opening must be at least equal to the sum of the areas of all
equipment vent connectors in the space.
NO combustion air openings are needed when the boiler (and other appliances) are installed
in a space with a volume NO LESS than 50 cubic feet per 1,000 Btuh of all appliances in
the space. That is, total the input of all appliances in MBH (1,000's of Btuh), then multiply
this total times 50. The building MUST NOT be of tight construction.
Example: For a total input of 1500 MBH (1,500,000 Btuh) and an 8-foot ceiling height,
the minimum volume would be 50 x 1500 = 75,000 cubic feet.
TM
SVF
WITHOUT other
appliances in room
TWO
openings, each at least:
1
Btuh
square inch per
of all appliances in the room,
2
.
but not less than 100 in
TWO
openings, each at least:
1
Btuh
square inch per
of all appliances in the room
— OR —
ONE
opening **, each at least:
1
Btuh
square inch per
of all appliances in the room
TWO
openings, each at least:
1
Btuh
square inch per
of all appliances in the room
— OR —
ONE
opening **, each at least:
1
Btuh
square inch per
of all appliances in the room
TWO
openings, each at least:
1
Btuh
square inch per
of all appliances in the room
— OR —
ONE
opening **, each at least:
1
Btuh
square inch per
of all appliances in the room
(continued)
boiler
1,000
Btuh
2
.
2,000
Btuh
3,000
Btuh
4,000
Btuh
3,000
Btuh
2,000
Btuh
3,000
Btuh
33