Weil-McLain SVF 1500 Manual page 36

Commercial condensing gas-fired water boilers
Hide thumbs Also See for SVF 1500:
Table of Contents

Advertisement

SVF
Series 1
Commercial Condensing Gas-Fired Water Boiler — Boiler Manual
DIRECT EXHAUST — Sidewall
Figure 29
Sidewall direct exhaust termination
Determine termination location
1. The vent termination must be installed as shown in Figure 29 and
in Figure 31, page 37.
2. The termination placement must comply with clearances and
limitations shown in Figure 28, page 35.
3. Locate the termination so is not likely to be damaged by foreign
objects, such as stones or balls, or subject to buildup of leaves or
sediment.
4. Ensure proper clearance above grade or snow line. Keep vents/
air intake area clear of accumulating snow.
5. Install the boiler in a location that allows proper routing of all vent
piping from the boiler vent connection to the selected sidewall
location.
Multiple vent terminations
1. When terminating multiple SVF
connection as described in this manual. See Figure 30, page 37
for typical layout.
2. Place wall penetrations to obtain minimum clearances shown in
Figure 29 for U. S. installations.
3. For Canadian installations, provide clearances required by Natural
Gas and Propane Installation Code - CAN/CSA B149.1 Installa-
tion Code and a ULC S636 compliant vent kit.
36
TM
boilers, terminate each vent
listed in Figure 22, page 27
Read and follow all instructions in this
manual.
through page 35.
Locate the termination such that the total
vent piping from the boiler to the termi-
nation
turer's instructions.
Provide a vent manufacturer's Vent Adapter
and reducer (if needed) at the boiler vent
connection.
Every joint on
ing must
supply locking collars could result in vent/
air piping leakage.
Install vent piping
USE SWEEP ELBOWS FOR ALL VENT PIPING
WHEN POSSIBLE — Short-radius elbows cause
higher pressure loss, resulting in less allowable
vent/air piping length. See Figure 25, page 31
for maximum lengths and reductions required
for fittings.
1. Install a vent manufacturer adapter if needed to adapt to the
vent size/material being used. Follow all vent manufacturer's
instructions.
2. Slope vent piping toward the boiler — slope vent piping a mini-
mum of ¼ inch per foot in horizontal runs or larger per vent pipe
manufacturer's instructions.
3. Support piping independently of the boiler — Install pipe sup-
ports every 5 feet on both the horizontal and vertical runs. Install
a hanger support within 6 inches of any upturn in the piping. Or
follow vent pipe manufacturer's instructions.
Install vent termination elbow
1. Maintain the required dimensions of the finished termination
piping as shown in Figure 29, page 36.
.
page 25
Figure 25, page 31
.
include a locking collar. Failure to
Part number 550-100-250/0819
-
-
-