KSB RPH Installation & Operating Manual

KSB RPH Installation & Operating Manual

Us units process pump
Table of Contents

Advertisement

Process Pump
RPH
US units
Installation/Operating Manual

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the RPH and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for KSB RPH

  • Page 1 Process Pump US units Installation/Operating Manual...
  • Page 2 All rights reserved. The contents provided herein must neither be distributed, copied, reproduced, edited or processed for any other purpose, nor otherwise transmitted, published or made available to a third party without the manufacturer's express written consent. Subject to technical modification without prior notice. © KSB SE & Co. KGaA, Frankenthal 23/07/2019...
  • Page 3: Table Of Contents

    Contents Contents Glossary .............................. 6 General.............................. 7 Principles ................................ 7 Installation of partly completed machinery.................... 7 Target group.............................. 7 Other applicable documents.......................... 7 Symbols ................................ 7 Key to safety symbols/markings........................ 8 Safety .............................. 9 General................................ 9 Intended use .............................. 9 Personnel qualification and training....................... 9 Consequences and risks caused by non-compliance with this manual ............ 10 Safety awareness ............................ 10 Safety information for the operator/user ..................... 10 Safety information for maintenance, inspection and installation .............. 10...
  • Page 4 Contents Checking the direction of rotation........................ 29 Commissioning/Start-up/Shutdown.................... 31 Commissioning/Start-up .......................... 31 6.1.1 Prerequisites for commissioning/start-up .................. 31 6.1.2 Filling in the lubricant ........................ 31 6.1.3 Shaft seal ............................ 33 6.1.4 Priming and venting the pump...................... 33 6.1.5 Final check ............................ 34 6.1.6 Water cooling............................. 34 6.1.7 Cooling the pump .......................... 34 6.1.8 Cooling the shaft seal ........................ 35 6.1.9...
  • Page 5 Contents 9.1.3 Design variants........................... 70 EU Declaration of Conformity ...................... 73 Certificate of Decontamination...................... 74 Index .............................. 75 5 of 80...
  • Page 6: Glossary

    Glossary Glossary Back pull-out design The complete back pull-out unit can be pulled out without having to remove the pump casing from the piping. Back pull-out unit Pump without pump casing; partly completed machinery Certificate of decontamination A certificate of decontamination is enclosed by the customer when returning the product to the manufacturer to certify that the product has been properly drained to eliminate any environmental...
  • Page 7: General

    In the event of damage, immediately contact your nearest KSB service facility to maintain the right to claim under warranty. 1.2 Installation of partly completed machinery To install partly completed machinery supplied by KSB refer to the sub-sections under Servicing/Maintenance.
  • Page 8: Key To Safety Symbols/Markings

    1 General Symbol Description Step-by-step instructions Note Recommendations and important information on how to handle the product 1.6 Key to safety symbols/markings Table 3: Definition of safety symbols/markings Symbol Description DANGER DANGER This signal word indicates a high-risk hazard which, if not avoided, will result in death or serious injury.
  • Page 9: Safety

    2 Safety 2 Safety All the information contained in this section refers to hazardous situations. DANGER In addition to the present general safety information the action-related safety information given in the other sections must be observed. 2.1 General ▪ This operating manual contains general installation, operating and maintenance instructions that must be observed to ensure safe operation of the system and prevent personal injury and damage to property.
  • Page 10: Consequences And Risks Caused By Non-Compliance With This Manual

    2 Safety 2.4 Consequences and risks caused by non-compliance with this manual ▪ Non-compliance with these operating instructions will lead to forfeiture of warranty cover and of any and all rights to claims for damages. ▪ Non-compliance can, for example, have the following consequences: –...
  • Page 11: Unauthorised Modes Of Operation

    2 Safety ▪ When taking the pump set out of service always adhere to the procedure described in the manual. (ð Section 6.1.13, Page 38) (ð Section 6.3, Page 40) ▪ Decontaminate pumps which handle fluids posing a health hazard. (ð Section 7.3, Page 49) ▪ As soon as the work has been completed, re-install and re-activate any safety- relevant devices and protective devices.
  • Page 12: Monitoring Equipment

    If the pump is to be operated at a higher temperature, if there is no data sheet or if the pump is part of a pool of pumps, contact KSB for the maximum permissible operating temperature. 2.9.3 Monitoring equipment The pump (set) must only be operated within the limits specified in the data sheet and on the name plate.
  • Page 13: Transport/Temporary Storage/Disposal

    1. On transfer of goods, check each packaging unit for damage. 2. In the event of in-transit damage, assess the exact damage, document it and notify KSB or the supplying dealer and the insurer about the damage in writing immediately.
  • Page 14: Storage/Preservation

    4. Always complete and enclose a certificate of decontamination when returning the pump. Indicate any safety measures and decontamination measures taken. (ð Section 11, Page 74) NOTE If required, a blank certificate of decontamination can be downloaded from the following web site: www.ksb.com/certificate_of_decontamination 14 of 80...
  • Page 15: Disposal

    3 Transport/Temporary Storage/Disposal 3.5 Disposal WARNING Fluids handled, consumables and supplies which are hot and/or pose a health hazard Hazard to persons and the environment! ▷ Collect and properly dispose of flushing fluid and any fluid residues. ▷ Wear safety clothing and a protective mask if required. ▷...
  • Page 16: Description Of The Pump (Set)

    Version with auxiliary impeller (inducer) Material variant to API 610 Nominal discharge nozzle diameter [mm] Nominal impeller diameter [mm] Special hydraulic system (type B) 4.3 Name plate KSB SE & Co. KGaA Johann-Klein-Straße 9 67227 Frankenthal Order No. Year 2019 Serial No.
  • Page 17: Design Details

    4 Description of the Pump (Set) 4.4 Design details Design ▪ Volute casing pump ▪ Horizontal installation ▪ Back pull-out design ▪ Single-stage ▪ Technical requirements to API 610 and ISO 9905 Pump casing ▪ Volute casing with integrally cast pump feet ▪...
  • Page 18: Configuration And Function

    Table 6: Bearing bracket designation Designation Description Back pull-out bearing bracket Size code (based on dimensions of seal chamber, shaft end and bearings) Bearings used Table 7: Bearing design KSB designation FAG designation SKF designation B.MUA B-MP-UA BECBM Table 8: Standard bearing assembly...
  • Page 19: Noise Characteristics

    4 Description of the Pump (Set) Impeller Shaft seal Rolling element bearing, pump end 10 Rolling element bearing, motor end Design The pump is designed with an axial fluid inlet and a radial or tangential outlet. The hydraulic system runs in its own bearings and is connected to the motor by a shaft coupling.
  • Page 20: Dimensions And Weights

    4 Description of the Pump (Set) Coupling ▪ Spacer-type multiple-disc coupling ▪ Coupling guard Baseplate ▪ Welded baseplate for pump and motor, in torsion-resistant design Special accessories ▪ As required 4.8 Dimensions and weights For dimensions and weights please refer to the general arrangement drawing/outline drawing of the pump/pump set.
  • Page 21: Installation At Site

    5 Installation at Site 5 Installation at Site 5.1 Safety regulations DANGER Excessive temperatures in the shaft seal area Explosion hazard! ▷ Never operate a pump (set) with gland packing in potentially explosive atmospheres. 5.2 Checks to be carried out prior to installation Place of installation WARNING Installation on mounting surface which is unsecured and cannot support the load...
  • Page 22: Installation On A Foundation

    5 Installation at Site 5.3.1 Installation on a foundation Fig. 6: Fitting the shims Bolt-to-bolt distance Shim Shim if (L) > 31.5 inches Foundation bolt ü The foundation has the required strength and characteristics. ü The foundation has been prepared in accordance with the dimensions given in the outline drawing/general arrangement drawing.
  • Page 23: Piping

    5 Installation at Site 5.4 Piping 5.4.1 Connecting the piping DANGER Impermissible loads acting on the pump nozzles Danger to life from escaping hot, toxic, corrosive or flammable fluids! ▷ Do not use the pump as an anchorage point for the piping. ▷...
  • Page 24: Permissible Forces And Moments At The Pump Nozzles

    5 Installation at Site 4. If required, install a filter in the piping (see drawing: Filter in the piping). Fig. 7: Filter in the piping Differential pressure gauge Filter NOTE Use a filter with laid-in wire mesh of 0.05 inches x 0.01 inches (mesh width x wire diameter) of corrosion-resistant material.
  • Page 25 5 Installation at Site Table 11: Forces and moments at the pump nozzles Suction nozzle Discharge nozzle Forces Moments Forces Moments [lbf] [ft×lbf] [lbf] [ft×lbf] 25-180 25-230 40-180 40-230 40-280 40-181 40-231 40-281 40-361 50-180 1400 1060 1900 50-230 1400 1060 1900 50-280 1400...
  • Page 26: Auxiliary Connections

    5 Installation at Site 5.4.3 Auxiliary connections DANGER Risk of potentially explosive atmosphere by incompatible fluids mixing in the auxiliary piping Risk of burns! Explosion hazard! ▷ Make sure that the barrier fluid or quench liquid are compatible with the fluid handled.
  • Page 27: Checking The Coupling Alignment

    5 Installation at Site 5.6 Checking the coupling alignment DANGER Inadmissible temperatures at the coupling or bearings due to misalignment of the coupling Explosion hazard! Risk of burns! ▷ Make sure that the coupling is correctly aligned at all times. CAUTION Misalignment of pump and motor shafts Damage to pump, motor and coupling!
  • Page 28: Electrical Connection

    Risk of injury by rotating shafts! ▷ Always operate the pump set with a coupling guard. If the customer specifically requests not to include a coupling guard in KSB's delivery, then the operator must supply one! ▷ Observe all relevant regulations for selecting a coupling guard.
  • Page 29: Earthing

    5 Installation at Site WARNING Incorrect connection to the mains Damage to the mains network, short circuit! ▷ Observe the technical specifications of the local energy supply companies. 1. Check the available mains voltage against the data on the motor name plate. 2.
  • Page 30 5 Installation at Site CAUTION Incorrect direction of rotation of model with auxiliary impeller (inducer) Damage to the pump! ▷ Separate the pump from the motor to check the direction of rotation. CAUTION Drive and pump running in the wrong direction of rotation Damage to the pump! ▷...
  • Page 31: Commissioning/Start-Up/Shutdown

    6 Commissioning/Start-up/Shutdown 6 Commissioning/Start-up/Shutdown 6.1 Commissioning/Start-up 6.1.1 Prerequisites for commissioning/start-up Before commissioning/starting up the pump set, make sure that the following conditions are met: ▪ The pump set has been mechanically connected as specified. ▪ The pump set has been properly connected to the power supply and is equipped with all protection devices.
  • Page 32 6 Commissioning/Start-up/Shutdown Fig. 11: Bearing bracket with constant level oiler Constant level oiler Vent plug Connection elbow of the constant Screw plug level oiler Bearing bracket Oil level sight glass 1. Remove the protective cage. 2. Unscrew the vent plug (2). 3.
  • Page 33: Shaft Seal

    6 Commissioning/Start-up/Shutdown Connecting the oil mist lubrication system (for oil mist lubrication only) Bearings with oil mist lubrication Fig. 12: Oil mist lubrication ü Always observe the instructions of the lubricating system manufacturer (especially on dosing and oil quantity). 1. Remove plugs 916.N3. 2.
  • Page 34: Final Check

    6 Commissioning/Start-up/Shutdown DANGER Risk of potentially explosive atmosphere inside the pump Explosion hazard! ▷ The pump internals in contact with the fluid to be handled, including the seal chamber and auxiliary systems, must be filled with the fluid to be handled at all times.
  • Page 35: Cooling The Shaft Seal

    6 Commissioning/Start-up/Shutdown Observe the following quality data of the cooling water: ▪ Maximum permissible cooling liquid pressure p = 145 psi ▪ Maximum permissible cooling liquid test pressure p = 215 psi ▪ Observe the specified cooling liquid quantity. 6.1.8 Cooling the shaft seal CAUTION Vaporisation pressure of fluid handled higher than atmospheric pressure Damage to the shaft seal/pump!
  • Page 36: Keeping Warm / Heating Up The Pump (Set)

    6 Commissioning/Start-up/Shutdown CAUTION Time for warming up the pump too short Damage to the pump! ▷ Check that the pump is sufficiently warmed up throughout. The casing cover can be heated with hot water or steam. Observe the following data for the heating medium: ▪...
  • Page 37: Checking The Shaft Seal

    6 Commissioning/Start-up/Shutdown DANGER Excessive temperatures due to dry running or excessive gas content in the fluid handled Explosion hazard! Damage to the pump set! ▷ Never operate the pump set without liquid fill. ▷ Prime the pump as per operating instructions. (ð Section 6.1.4, Page 33) ▷...
  • Page 38: Shutdown

    6 Commissioning/Start-up/Shutdown 6.1.13 Shutdown ü The shut-off element in the suction line is and remains open. ü On pump sets with double mechanical seal, apply the required pressure specified in the general arrangement drawing to the mechanical seal chamber also during standstill.
  • Page 39: Ambient Temperature

    6 Commissioning/Start-up/Shutdown 6.2.1 Ambient temperature CAUTION Operation outside the permissible ambient temperature Damage to the pump (set)! ▷ Observe the specified limits for permissible ambient temperatures. Observe the following parameters and values during operation: Table 14: Permissible ambient temperatures Permissible ambient temperature Value Maximum 122 °F...
  • Page 40: Shutdown/Storage/Preservation

    6 Commissioning/Start-up/Shutdown = 0.3 × Q The data refer to water and water-like fluids. Longer operating periods with these fluids and at the flow rates indicated will not cause an additional increase in the temperatures on the pump surface. However, if the physical properties of the fluids handled differ from those of water, the calculation formula below must be used to check if an additional heat build-up may lead to a dangerous temperature increase at the pump surface.
  • Page 41: Returning To Service

    6 Commissioning/Start-up/Shutdown The pump (set) is removed from the pipe and stored ü The pump has been properly drained. (ð Section 7.3, Page 49) ü The safety instructions for dismantling the pump have been observed. (ð Section 7.4.1, Page 49) 1. Spray-coat the inside wall of the pump casing and, in particular, the impeller clearance areas with a preservative.
  • Page 42: Servicing/Maintenance

    7 Servicing/Maintenance 7 Servicing/Maintenance 7.1 Safety regulations DANGER Improper cleaning of coated pump surfaces Explosion hazard by electrostatic discharge! ▷ When cleaning coated pump surfaces in atmospheres of Explosion group IIC, use suitable anti-static equipment. DANGER Sparks produced during servicing work Explosion hazard! ▷...
  • Page 43: Servicing/Inspection

    NOTE All maintenance work, service work and installation work can be carried out by KSB Service or authorised workshops. For contact details please refer to the enclosed "Addresses" booklet or visit "www.ksb.com/contact" on the Internet.
  • Page 44 7 Servicing/Maintenance DANGER Incorrectly serviced barrier fluid system Explosion hazard! Fire hazard! Damage to the pump set! Hot and/or toxic fluids escaping! ▷ Regularly service the barrier fluid system. ▷ Monitor the barrier fluid pressure. CAUTION Increased wear due to dry running Damage to the pump set! ▷...
  • Page 45: Inspection Work

    7 Servicing/Maintenance CAUTION Operation outside the permissible bearing temperature Damage to the pump! ▷ The bearing temperature of the pump (set) must never exceed 194 °F (measured on the outside of the bearing bracket). 7.2.2 Inspection work DANGER Excessive temperatures caused by friction, impact or frictional sparks Explosion hazard! Fire hazard! Damage to the pump set!
  • Page 46 7 Servicing/Maintenance Suction-side casing wear ring Discharge-side casing wear ring Inside Diametral clearance Inside Diametral clearance diameter diameter As-supplied Worn As-supplied Worn [inch] Nominal Min. Max. Max. Nominal Min. Max. Max. 50-280 4,724 0,024 0,028 0,047 4,724 0,024 0,028 0,047 50-360 4,724 0,024...
  • Page 47: Lubrication And Lubricant Change Of Rolling Element Bearings

    +347 °F HD 20W/20 SAE Cleveland) Solidification point 59 °F (pour point) Application Higher than temperature permissible bearing temperature At least once a year For ambient temperatures below 15 °F use a different suitable type of lubricating oil. Contact KSB. 47 of 80...
  • Page 48 7 Servicing/Maintenance 7.2.3.1.3 Oil quantity Bearing bracket Oil quantity bearing bracket [gal] 0.23 0.47 0.66 1.50 1.24 7.2.3.1.4 Changing the oil WARNING Lubricants posing a health hazard and/or hot lubricants Hazard to persons and the environment! ▷ When draining the lubricant take appropriate measures to protect persons and the environment.
  • Page 49: Drainage/Cleaning

    7 Servicing/Maintenance 7.3 Drainage/cleaning WARNING Fluids handled, consumables and supplies which are hot and/or pose a health hazard Hazard to persons and the environment! ▷ Collect and properly dispose of flushing fluid and any fluid residues. ▷ Wear safety clothing and a protective mask if required. ▷...
  • Page 50: Preparing The Pump Set

    7 Servicing/Maintenance DANGER Insufficient preparation of work on the pump (set) Risk of injury! ▷ Properly shut down the pump set. (ð Section 6.1.13, Page 38) ▷ Close the shut-off elements in the suction line and discharge line. ▷ Drain the pump and release the pump pressure. (ð Section 7.3, Page 49) ▷...
  • Page 51: Removing The Impeller

    7 Servicing/Maintenance 7.4.5 Removing the impeller 7.4.5.1 Loosening the impeller — for bearing brackets B02 to B05 ü The notes and steps stated in (ð Section 7.4.1, Page 49) to (ð Section 7.4.4, Page 50) have been observed/carried out. ü The back pull-out unit has been placed in a clean and level assembly area. 1.
  • Page 52: Dismantling The Bearing Assembly

    7 Servicing/Maintenance 7.4.7 Dismantling the bearing assembly ü The notes and steps stated in (ð Section 7.4.1, Page 49) to (ð Section 7.4.6, Page 51) been observed/carried out. ü The bearing bracket has been placed in a clean and level assembly area. 1. Unscrew the hexagon socket head cap screw in the coupling hub. 2.
  • Page 53: Installing The Bearing Assembly

    7 Servicing/Maintenance Sequence Always reassemble the pump in accordance with the corresponding general assembly drawing. Sealing elements ▪ Gaskets – Always use new gaskets, making sure that they have the same thickness as the old ones. – Always fit gaskets of asbestos-free materials or graphite without using lubricants (e.g.
  • Page 54: Fitting The Shaft Seal

    7 Servicing/Maintenance 5. Use a C-spanner to tighten slotted round nut 920.21 (right-hand thread) without lock washer 931.01. 6. Let angular contact ball bearing 320.01 cool down to approximately 9 °R above ambient temperature. 7. Re-tighten slotted round nut 920.21, then unscrew it again. 8.
  • Page 55: Fitting The Impeller

    7 Servicing/Maintenance 4. On cooled versions, watch O-rings 412.01/.31 at casing cover 161. 5. Screw casing cover 161 to complete bearing bracket 330 with hexagon nuts 920.15. 7.5.4 Fitting the impeller 7.5.4.1 Fitting the impeller — for all bearing bracket sizes ü...
  • Page 56: Installing The Back Pull-Out Unit

    7 Servicing/Maintenance 7.5.5 Installing the back pull-out unit WARNING Back pull-out unit tilting Risk of crushing hands and feet! ▷ Suspend or support the bearing bracket at the pump end. ü The notes and steps stated in (ð Section 7.5.1, Page 52) to (ð Section 7.5.4, Page 55) have been observed and carried out. ü...
  • Page 57: Tightening Torques

    7 Servicing/Maintenance 7.6 Tightening torques 7.6.1 Tightening torques for the pump Use a torque wrench to tighten the screwed connections (902.01/920.01) between the volute casing and the casing cover. Table 20: Tightening torques for bolted/screwed connections Material A 193 Grade B7/ A 193 Grade B7/ 10.9 A276 Type 316 Ti /...
  • Page 58 7 Servicing/Maintenance Material A 193 Grade B7/ A 193 Grade B7/ 10.9 A276 Type 316 Ti / B16 / Type 420 (Asia and Americas) A 540 Grade B24 Material 1.7709/1.6772 C35E+QT A4-70 1.4571/1.4021 (Monix 3K) (Europe) Stud Stud 902.15 Hexagon head bolt Stud 902.02 Impeller nut 922.01 901.37 and impeller screw...
  • Page 59 7 Servicing/Maintenance Material A 193 Grade B7/ A 193 Grade B7/ 10.9 A276 Type 316 Ti / B16 / Type 420 (Asia and Americas) A 540 Grade B24 Material 1.7709/1.6772 C35E+QT A4-70 1.4571/1.4021 (Monix 3K) (Europe) Stud Stud 902.15 Hexagon head bolt Stud 902.02 Impeller nut 922.01 901.37 and impeller screw...
  • Page 60: Tightening Torques For The Shaft Nut

    7 Servicing/Maintenance 7.6.2 Tightening torques for the shaft nut Fig. 14: Shaft nut position Table 21: Shaft nut tightening torques Position Bearing bracket Slotted round Thread Tightening torques [ft×lbf] 920.21 M 40x1,5 KM11 M 55x2 KM15 M 75x2 KM24 M 120x2 KM24 M 120x2 7.7 Spare parts stock 7.7.1 Ordering spare parts...
  • Page 61: Recommended Spare Parts Stock For 2 Years' Operation To Din 24296

    7 Servicing/Maintenance 7.7.2 Recommended spare parts stock for 2 years' operation to DIN 24296 Table 22: Quantity of spare parts for recommended spare parts stock Part No. Description Number of pumps (including stand-by pumps) 6 and 7 8 and 9 10 and more Shaft 20 %...
  • Page 62: Interchangeability Of Pump Components

    7 Servicing/Maintenance 7.7.3 Interchangeability of pump components Components featuring the same number in a column are interchangeable. Table 23: Interchangeability of pump components Description Part. No. B02S 25-180 1 1 1 1 1 1 1 1 1 25-230 1 1 1 1 1 1 1 1 1 40-180 1 1 1 1 1...
  • Page 63 7 Servicing/Maintenance Description Part. No. B05L 200-450 3 3 3 4 3 3 3 3 5 200-501 3 3 3 3 3 3 3 3 5 250-401 3 3 3 3 3 3 3 3 5 250-501 3 3 3 3 3 3 3 3 5 300-400 3 3 3 3 3...
  • Page 64: Trouble-Shooting

    If problems occur that are not described in the following table, consultation with the KSB service is required. A Pump delivers insufficient flow rate B Motor is overloaded...
  • Page 65 In the case of persistent overloading, turn down impeller. ✘ - Density or viscosity of fluid handled Contact KSB. higher than stated in purchase order - Speed is too high. Reduce speed. ✘ ✘ ✘...
  • Page 66: Related Documents

    9 Related Documents 9 Related Documents 9.1 General assembly drawings with list of components 9.1.1 Bearing brackets B02 to B05 Fig. 15: Bearing brackets B02 to B05, a) uncooled and b) cooled Table 25: List of components, bearing brackets B02 to B05 Part No.
  • Page 67 9 Related Documents Part No. Comprising Description 920.15 Hexagon nut Shaft 920.21 Slotted round nut 931.01 Lock washer 940.01/.02 Impeller 931.02 Lock washer 503.01/.02 Impeller wear ring 904.06/.07 Grub screw 411.31/.32/.67 Joint ring 320.02/550 Angular contact ball bearing with disc 550 (adjusting washer) 322.01 322.01 Cylindrical roller bearing...
  • Page 68: Bearing Brackets B06 And B07

    9 Related Documents Part No. Comprising Description 70-3 411.41 Joint ring 724.01 Blind flange 901.20 Hexagon head bolt 920.20 Hexagon nut 550.20 Disc 831.02 831.02 Fan impeller Fan hood 485.02 Fan hub 904.37 Grub screw 922.01 922.01 Impeller nut 99-9 99-9 Set of sealing elements, complete 9.1.2 Bearing brackets B06 and B07...
  • Page 69 9 Related Documents Part No. Comprising Description Casing cover 411.10 Joint ring 412.01/.31 O-ring 502.02 Casing wear ring 901.30 Hexagon head bolt 902.15 Stud 904.04 Grub screw 916.16 Screw plug 920.15 Hexagon nut Shaft 920.21 Slotted round nut 931.01 Lock washer 940.01/.02 Impeller 503.01/.02...
  • Page 70: Design Variants

    9 Related Documents Part No. Comprising Description 70-3 70-3 Drain line 411.01 Joint ring 902.42 Stud 920.42 Hexagon nut 550.42 Disc 723.23 Flange 744.07 Gate valve 710.21 Pipe 723.21 Flange 411.41 Joint ring 24.01 Blind flange 901.20 Hexagon head bolt 920.20 Hexagon nut 550.20...
  • Page 71 9 Related Documents Design Detailed view Design with plug 916.01 D01044 Design with welded drain Design with bearings in tandem arrangement D01043 320.02 71 of 80...
  • Page 72 9 Related Documents Design Detailed view Design with heatable casing D01126 Design with auxiliary impeller 23-2 72 of 80...
  • Page 73: Eu Declaration Of Conformity

    10 EU Declaration of Conformity 10 EU Declaration of Conformity Manufacturer: KSB SE & Co. KGaA Johann-Klein-Straße 9 67227 Frankenthal (Germany) The manufacturer herewith declares that the product: KSB order number: ....................▪ is in conformity with the provisions of the following Directives as amended from time to time: –...
  • Page 74: Certificate Of Decontamination

    11 Certificate of Decontamination 11 Certificate of Decontamination Type: ..........................Order number/ Order item number ..........................Delivery date: ..........................Applications: ..........................Fluid handled ..........................Please tick where applicable ⃞ ⃞ ⃞ ⃞ ⃞ Corrosive Oxidising Flammable Explosive Hazardous to health ⃞...
  • Page 75: Index

    Index Index Installation Installation on a foundation 22 Abrasive fluids 40 Installation at site 21 Auxiliary connections 26 Intended use 9 Interchangeability of pump components 62 Back pull-out unit 50 Bearing temperature 44 Keeping warm 36 Bearings 17 Key to safety symbols/markings 8 Certificate of Decontamination 74 List of components 66, 68 Clearances 45 Commissioning 31 Constant level oiler 31 Maintenance 43...
  • Page 76 Index Spare part Ordering spare parts 60 Special accessories 20 Start-up 37 Storage 14, 41 Temperature difference 36 Temperature limits 11, 12 Tightening torques 57 Shaft nut 60 Transport 13 Warnings 8 Warranty claims 7 Water cooling 34, 35 76 of 80...
  • Page 80 KSB SE & Co. KGaA Johann-Klein-Straße 9 • 67227 Frankenthal (Germany) Tel. +49 6233 86-0 www.ksb.com...

Table of Contents

Save PDF