Procedure
Step 1 Remove an appropriate length of the insulation layer from the ground cables using a wire
stripper, as shown in
Figure 5-5 Stripped length
Step 2 Insert the exposed core wires into the conductor crimp area of the OT terminal and crimp
them using hydraulic pliers, as shown in
Figure 5-6 Crimping a cable
Step 3 Remove the ground screws from the ground points.
The following uses ground points 1 and 4 as examples to describe how to connect the ground
cables.
Step 4 Remove the locking caps at the GND and AC OUTPUT waterproof cable connectors at the
bottom of the SUN2000.
Step 5 Remove the plugs from the locking caps and route the ground cables into the locking caps.
Step 6 Put the PV side and protection ground cables into the GND and AC OUTPUT connectors at
the bottom of the SUN2000, respectively.
Issue Draft C (2016-01-12)
Select ground points for PV side grounding and protective grounding based on the principle of easy
operation.
For the system with multiple SUN2000s, connect the ground cables of each SUN2000 to a ground
bar in equipotential mode.
Figure
The crimping must result in full containment of the cable conductors and complete contact between the
cable conductors and the terminal.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5-5.
Figure
5-6.
5 Electrical Connections
56

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sun2000-25ktl-us

Table of Contents