7-7
How to Set Up the Directional
Valve Linkage
Note: Adjustment of the oscillate directional valve
linkage is only necessary when the linkage or valve
has been replaced.
Note: Perform this procedure with the machine on
a firm, level surface with the boom in the stowed
position.
1
Use a "bubble type" level to verify the working
surface is completely level.
Tip-over hazard. Failure to
perform this procedure on a level
floor could compromise the
stability of the machine resulting
in the machine tipping over.
2
Check the tire pressure in all four tires and add
air if needed to meet specification.
Note: The tires on some machines are foam-filled
and do not need air added to them.
3
Remove the non-steer end drive chassis cover
and axle covers.
4
Remove the ball joint retaining fastener from
the bracket.
5
To level the drive chassis, start the engine and
push up or pull down on the threaded rod until
the machine is completely level.
6
Verify that the ground and drive chassis are
completely level.
Part No. 1286829GT
S-40 XC • S-45 XC • S-40 TraX • S-45 TraX
7
Adjust the ball joint until the hole lines up with
the retaining fastener hole in the bracket.
8
Install the ball joint to the axle and tighten the
jam nut.
9
Check to be sure the drive chassis is
completely level.
10 Measure the distance between the drive
chassis and the non-steer axle on both sides
(from the inside of the drive chassis).
Note: If the distance is not equal and the
adjustment to the linkage was completed with the
ground and drive chassis level, repeat steps 5
through 10 OR consult Genie Product Support.
Service and Repair Manual
Manifolds
71

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

S-40 traxS-40 xcS-45 trax

Table of Contents