Router lift
Table of Contents

Advertisement

If you have the Downdraft Dust
13
Collection Box (RT-DCB) installed under
your router table, pass the power cord
of your router through the power cord
clamp in the side of the Downdraft Dust
Collection Box.
Use a Phillips screwdriver to remove the
screws holding either the top or bottom
half of the clamp. Move that half of the
clamp out of the way to pass the power
cord through the clamp, then replace
the removed half-clamp and re-install
the screws.
i
Leave enough excess power cord (i.e., approximately 18") between the bottom of the router and the
power cord clamp to allow the router and router lift to be lifted all the way out of the opening in the
router table.
Turn the insert ring counter-clockwise to
14
reinstall.
RT-LFT/RT-DCB OWNER'S MANUAL