Leak Testing; Before Commissioning - REMKO KWL 130 Operation Manual

Air-cooled chiller and air-cooled chiller with heat pump function
Table of Contents

Advertisement

REMKO KWL (H)

Leak testing

Leak testing is carried out after all
the pipes and fittings have been
connected.
1. Flush the system twice with
water.
2. Clean the sieve insert of the dirt
trap provided by customer.
3. Fill the system with water again
and vent the system at the
manual air bleeder.
4. Adjust the test pressure to
250 kPa (2.5 bar).
5. Check the connections after a pe-
riod of 24 hrs for leaking water.
If water is visible, the connection
has not been secured.
Tighten the connection or make a
new connection.
6. After a successful leak test, re-
move the excess pressure from
the medium line. If a water-
glycol mixture is used, adjust
the non circulating pressure as
required.
9
Unit preliminary pressure
Unit preliminary
pressure
34
Before
commissioning
Filling the system
The system is filled on-site at the
filling and draining connection.
Anti-freeze protection for the medium
If a water-glycol mixture is used,
it is to be pre-mixed before being
put in the system. The desired con-
centration is then to be checked.
Unit preliminary pressure for the
medium
The preliminary pressure of the
medium (without operation of the
circulation pump) varies within
the system. From the highest
point, the pressure increases by
approx.10 kPa (0.1bar) per metre
difference in altitude (geodetic
altitude). The value measured at
the highest point is identified as
the standstill pressure.
The position of the unit in the
system is decisive in the calculation
of the unit's preliminary pressure
(pressure of the manometer on
the unit installed by the customer).
The pressure is to be set to at least
70 kPa (0.7 bar).
Non-circulating
pressure
Unit preliminary
pressure
Geodetic
System altitude
If the unit is positioned at the
lowest point in the system,
the unit preliminary pressure
(=standstill pressure+geodetic
system altitude) must be set to
at least 70 kPa (0.7 bar) + 10
kPa (0.1bar) x geodetic system
altitude.
If the unit is positioned at the
highest point in the system,
the unit preliminary pressure
(=standstill pressure) must be
set to at least 70 kPa (0.7 bar).
Please note that the system
pressure at the lowest point
is increased by the geodetic
system altitude!
Bleeding the system
Air may still be in the pipe
lines after the leak test. This is
carried during operation of the
circulation pump to the next
highest point or to the cold
water drain. Here it is necessary
to vent again (Figure 10).
Also vent the pump if neces-
sary.
The standstill pressure must
then be adjusted to the re-
quired system pressure.
10
Manual bleeding
MAG
The preliminary pressure for the
diaphragm expansion vessel must
be adjusted individually to the
system layout, the volume of the
medium and the installation site.
Manual
bleeder