LIFT FROM THE STREET TO THE SET UP
LOCATION
If the base allows, the simplest thing is to use a pallet
truck to move the AMS 10 to the set up location.
NOTE
The centre of gravity is offset to one side (see
print on the packaging).
If AMS 10 needs to be transported across soft ground,
such as a lawn, we recommend that a crane truck is
used that can lift the unit to the installation location.
When AMS 10 is lifted with a crane, the packaging must
be undamaged and the load distributed with a boom,
see the illustration above.
If a crane cannot be used AMS 10 can be transported
using an extended sack truck. AMS 10 must be used
on the side marked "heavy side" and two people are re-
quired to get the AMS 10 up.
LIFT FROM THE PALLET TO FINAL
POSITIONING
Before lifting remove the packaging and the securing
strap to the pallet.
Place lifting straps around each machine foot. Lifting
from the pallet to the base requires four persons, one
for each lifting strap.
It is not permitted to lift anything other than the machine
feet.
SCRAPPING
When scrapping, the product is removed in reverse or-
der. Lift by the bottom panel instead of a pallet!
10
Chapter 2 | Delivery and handling
CONDENSATION RUN OFF
Condensation runs out on to the ground below AMS 10.
To avoid damage to the house and heat pump, the
condensation must be gathered and drained away.
NOTE
It is important to the heat pump function that
condensation water is led away and that the
drain for the condensation water run off is not
positioned so that it can cause damage to the
house.
NOTE
To ensure this function, the accessory KVR 10
should be used. (Not included)
NOTE
The electrical installation and wiring must be
carried out under the supervision of an author-
ised electrician.
NOTE
Self regulating heating cables must not be
connected.
• The condensation water (up to 50 litres / 24 hrs) must
be routed away by a pipe to an appropriate drain, it is
recommended that the shortest outdoor length pos-
sible is used.
• The section of the pipe that can be affected by frost
must be heated by the heating cable to prevent
freezing.
• Route the pipe downward from AMS 10.
• The outlet of the condensation water pipe must be at
a depth that is frost free or alternatively indoors (with
reservation for local ordinances and regulations).
• Use a water trap for installations where air circulation
may occur in the condensation water pipe.
• The insulation must be tight against the bottom of the
condensation water trough.
Drain pan heater, control
The drain pan heater is supplied with power when one
of the following conditions is met:
1.
The compressor has been in operation for at least
30 minutes after last start.
2.
The ambient temperature is lower than 1 °C.
NIBE AMS 10

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ams 10-6Ams 10-12Ams 10-16Ams 10 series

Table of Contents