Preparation For Installation - Toyota Avalon GSX30 Series Manual

Table of Contents

Advertisement

Less than
3 mm
Puncher
20 − 30 mm
Air Saw
INTRODUCTION

2. PREPARATION FOR INSTALLATION

(a) SPOT WELD POINTS
(1) When welding panels with a combined thickness of
over 3 mm (0.12 in.), use a MIG (Metal Inert Gas)
welder for plug welding.
HINT: Spot welding will not provide sufficient durability
for panels over 3 mm (0.12 in.) thick.
F10011A
(b) APPLICATION OF WELD-THROUGH PRIMER
(SPOT SEALER)
(1) Remove the paint from the portion of the new parts
and body to be welded, and apply weld-through prim-
er.
F10012A
(c) MAKING HOLES FOR PLUG WELDING
(1) For areas where a spot welder cannot be used, use a
puncher or drill to make holes for plug welding.
REFERENCE:
Thickness of welded portion
1.0 (0.04) under
1.0 (0.04) − 1.6 (0.06)
1.7 (0.07) − 2.3 (0.09)
F10013A
2.4 (0.09) over
(d) SAFETY PRECAUTIONS FOR ELECTRICAL COM-
PONENTS
(1) When welding, there is a danger that electrical compo-
nents will be damaged by the electrical current flowing
through the body.
(2) Before starting work, disconnect the negative terminal
of the battery and ground the welder near the welding
location of the body.
F10014A
(e) ROUGH CUTTING OF JOINTS
(1) For joint areas, rough cut the new parts, leaving 20 −
30 mm (0.79 − 1.18 in.) overlap.
Overlap
F10015A
IN-11
mm (in.)
Size of plug hole
5 (0.20) ø over
6.5 (0.26) ø over
8 (0.31) ø over
10 (0.39) ø over

Hide quick links: