11. Remove auger motor bracket with 8 screws (Fig. 9).
12. Remove bag pin bracket with two thumbscrews (Fig. 9).
13. The units width may be further reduced by removing the
upper ice storage section (Fig. 10). This reduces unit width
by 45mm (1.75") to an overall width of 864mm (34").
a) Remove window.
b) Pull window interlock switch cable through wire trough in
upper right corner of base (Fig. 10.1).
c) Cut tie wrap.
d) Release latch from each side of ice storage section
(Fig. 10.2).
e) Lift upper ice storage section from base.
Note:
Reinstallation of auger tube requires locating slot be in
the 7 o'clock position and upper end of auger be flush to
auger motor bracket.