Bed Pan Flusher / Sanitizer - Energy Saver
With Hands Free Operation
Operation, Maintenance and Installation Manual
Sequence of Operation
1.
Providing machine is installed into position with power and water connected push power on
button.
2.
When the unit is turned on via the display panel the display shows fill indicating steam
generator and cold water tanks are filling to the high water level.
At this stage the unit will not commence a cycle until Step 5.
3.
Once the steam tank water level probes sense the tank is full it will start heating.
4.
The steam tank is heated to temperature 90° C - 9 2° C. The machine is now ready to
commence a cycle.
The display shows rdy (ready).
5.
The operator breaks the infra-red beam, which opens the door.
The display shows open.
Note: Whenever the door is opened the elements are in the off mode.
Issue 24
10
Page
rd
23
August 2013