ASSEMBLY OF THE OCTO+ POOL STRUCTURE
> >
The pool structure is mounted in two stages:
- Stage 1, excavation of the site and installation of the cradles designed to
reinforce the lateral walls. A cradle comprises a cross beam, vertical posts and
metallic plates to be bolted together.
- Stage 2, assembly of the wooden structure and fi tting of the additional items
(liner, coping, etc.).
We recommend that the pool structure be
assembled by two people.
Before you begin, familiarise yourself with
the nomenclature page (enclosed with the
Accessories kit) and the main exploded
view (at the end of this document) that
corresponds to your pool.
19
540 & 640 cm x 120 cm
540 & 640 cm x 133 cm
You will need to dig shallow trenches to hold the cradles. Make sure that these are parallel to each other and to the A2 axle. The
number of trenches required will depend on the pool model, refer to the illustrations corresponding to your pool. Trenches should be
regular and sized to hold the cradles in the right position. Only one trench is requried for the Octo 460.
21
Lay the cradle components out beside the trench and fi t them together (using the cradle kit).
23
Once the cradles have been assembled, place them in the trenches and block them in position using wet compacted sand
if necessary. During this operation, check that the cradles are level, straight, aligned and parallel. Fill the trenches with wet,
10
compacted sand. Important ! Make sure that the cradles are buried to the correct depth.
proswell.fr
/ OCTO & OCTO+
P
34 cm
20 cm
640 cm x 146 cm
20 cm
460 cm x 120 cm
34 cm
20
L
62 cm
62 cm
62 cm
22
24
Cr
oss section of the cement slab
In the case of a cement slab, it is
better to seal the cradles into the
slab and create a peripheral drain.