Table 1-1 Move Preparation Checklist - Honeywell FSC-SM Installation Manual

Safety manager
Table of Contents

Advertisement

1.3
Move Preparation,
Checklist
4
Continued
Table 1-1 provides a checklist to be used when planning the movement of
FSC Safety Manager cabinets.
Table 1-1 – Move preparation checklist
Check
Action
Travel Route
1
Space
2
3
Floor Loading
Power Distribution Check for proper transformer sizes, distribution
4
Grounding
5
Conduits and
6
Cable Trays
Environment
7
8
Security
Responsibilities
9
10
Communications
For additional information regarding actions described in the
Move Preparation Checklist, refer to SM02-550 — TPS System Site
Planning Manual in the Binder TPS 3020-1 System Site Planning-1.
FSC Safety Manager Installation Guide
Chart the equipment's route of travel regarding:
• loading doors — height and location,
• elevators — size, capacity, and availability,
• aisles — number, size, and layout,
• doorways — number and size,
• hallways — size, restrictions, and bends,
• stairs and ramps — may require some type of
lifting, and
• rigging of equipment — if needed.
Is there enough space to hold the equipment?
Will the floor in all areas be strong enough?
panels and sufficient outlets for support, test and
maintenance equipment.
Be sure that proper grounds are available.
Make sure that conduits and cable trays are
large enough and the proper type to
accommodate all of the required cables.
Are lighting and other environmental
requirements adequate?
Provide security clearances for the installation
crew if it is not composed of regular employees.
Are all responsibilities clearly defined and
understood?
At minimum, three conveniently located
telephones are needed for:
• Honeywell Technical Assistance Center (TAC)
data terminal,
• Honeywell TAC voice, and
• Operator Emergency.
Notes