Site Inspections

Inspection Overview

2

Deficiencies

What to Inspect

Antenna and Tower
Inspections
2-2
Inspect the site to verify that the necessary equipment has been properly
installed. Also, as part of the inspection, verify that the equipment is
adequate to support the Motorola equipment. Not all inspections may
apply to every site. The site characteristics determine which inspections
apply.
Notify responsible persons of any deficiencies as soon as possible, if the
installer is not responsible for correcting the noted deficiencies.
Deficiencies may need to be corrected before any installation can start.
The following external items should be inspected and compared against
any related site-specific documentation.
S
Towers
S
Antennas
S
External ground systems
S
Clearances for units
S
Mounting Structures
Additionally, for all sites the incoming power should be inspected and
compared against any related site-specific documentation.
Documentation
The vendor responsible for supplying the towers should leave the
installation documentation at the site after the tower has been erected.
Review this documentation and compare it with any related site-specific
documents.
Inspection
Inspect the following:
S
Tower painting
S
Tower lighting (beacons)
S
Antenna and transmission line installation
S
Grounding.
SCt300 1X BTS Hardware Installation, ATP, and FRU Procedures
NOTE
Installation of ancillary equipment (e.g., power supplies,
terminal blocks, etc.) may be the responsibility of the
installer. Refer questions to your Motorola Program
Manager.
JAN 2002
DRAFT