Prepare Site for the Arrival of the Equipment

Description

2

Equipment Arrival

Securing Fluorescent Lights

Figure 2-1: Securing Lights with Tape
2-6
This information covers various topics not all of which are needed at
every site. Based on the site characteristics execute the steps that apply
to your site. Before installing the equipment, do the following to ensure
the safety of installation personnel and to protect the equipment.
Before the equipment arrives, indicate to the transport company an area
at the site where the equipment can be unloaded and, if necessary,
unpacked. The equipment should be carefully delivered to the site, along
with all equipment dollies and padding required to safely move the
equipment from the unloading area to the cell site. The following should
also be provided, outdoor weather protection, temporary lighting and
power for lighting and power tools.
Figure 2-1 illustrates the use of tape to secure fluorescent tubes. Secure
any fluorescent tubes that may be hit or damaged by any unit, cable, or
personnel.
Apply masking tape to keep
fluorescent tubes in place in
the fixtures.
SCt300 1X BTS Hardware Installation, ATP, and FRU Procedures
0150–O_IL.doc
JAN 2002
DRAFT

Advertisement

Table of Contents
loading

Table of Contents