CONTENTS OF THIS DOCUMENT SHALL NOT BECOME PART OF OR MODIFY ANY CONTRACT BETWEEN THE PARTIES. In no event will Eaton be responsible to the purchaser or user in contract, in tort (including negligence), strict liability or other-wise for any special, indirect, incidental or consequential damage or loss whatsoever, including but not limited to...
FOR LIFE FOR LIFE Eaton meets or exceeds all applicable industry standards relating to product safety in its Cooper Power™ series products. We actively promote safe practices in the use and maintenance of our products through our service literature, instructional training programs, and the continuous efforts of all Eaton employees involved in product design, manufacture, marketing, and service.
Hazardous Voltage. All associated apparatus must be de-energized during any hands-on installation or main- Introduction tenance. Failure to comply could result in death and Eaton's Cooper Power series 600 A 15/25 kV Class severe personal injury. PUSH-OP ® deadbreak connectors are used to terminate high-voltage underground cable on deadfront apparatus such as transformers, switches, and switchgear.
Figure 3. Cutback dimensions for concentric neutral cable. Cable preparation ote: If a non-Eaton 600 A T-body is being used, use the stripback lengths given in the T-body kit, then proceed to Step 7 of these instructions. Step 3 Install CA625 cable adapter Step 1 •...
Page 7
Step 4 PLACE FIRST Cable insulation cutback COMPRESSION CONNECTOR CRIMP HERE • There should be between 4-3/8" and 4-11/16" of exposed cable beyond the cable adapter. Cut the cable insulation even with the end of the cable adapter and remove the CA625 protruding cable insulation.
Page 8
Step 7 PUSH-OP ASSEMBLY Install LRTP into T-Body T-WRENCH • Clean and then lubricate the mating 600 A interface of the LRTP and T-body with the lubricant supplied. • Remove and recycle the shipping cap from the 200 A LRTP interface and the thread protector from the alignment segment.
Install PUSH-OP deadbreak connector on apparatus • Release operating eye from clampstick. bushing • Push forward on push plate firmly with clampstick until a bump is felt and latch plate fully engages locking teeth. Step 9 (Refer to Figure 13a.) Install PUSH-OP deadbreak connector on apparatus LOCKING PUSH PLATE...
Page 10
• If present, thread optional locking pin with clampstick to • If optional locking pin is used, pull on latch plate's secure connection. (Refer to Figure 13c.) operating eye with clampstick to verify latch plate is still engaged in locking teeth after locking pin is tightened. (Refer to Figure 13e.) OPTIONAL LOCKING PIN LATCH PLATE...
Page 11
Step 11 Ground system • Connect drain wire on insulated protective cap to system ground. • Connect drain wire to LRTP grounding tab and shroud grounding tab. • Connect drain wire to PUSH-OP body grounding tab and shroud grounding tab. •...