ROUTING

The customer is solely liable for routing of components from dock to final site.
GE must be able to move system components in or out with no need to uncrate or disassemble any of the
components. The entire passageway must be cleared, adequately lighted and free from dust.
The floor and its surfacing must be able to withstand the live load of components and handling
equipment.
Floor surfacing must be continuous.
The customer must protect any fragile flooring surfaces.
MINIMUM SPECIFICATIONS FOR MAGNET ROUTING
Floor must be able to withstand a moving load of 5352 daN
Height: 2.5m [98.5in], width: 2.5m [98.5in]
1154
[45.4 in]
2282
[89.8 in]
FRONT VIEW OF MAGNET
Recommended minimum opening for side (wall) delivery : 2500 [98.5in] (width) x 2500 [98.5in] (height)
STRAIGHT PATH
(Rigging wheels required)
2700
[106.3 in]
STORAGE CONDITIONS
System components except the magnet should be stored in a cleaned room.
condensing.
Material should not be stored for more than 90 days.
The magnet will be delivered after GE validation of the site.
INSTALLATION AND DELIVERY ACCEPTANCE
A survey of the site established by the customer and GE will make the
decision for the delivery time.
This survey of the site (a form is made available by GE) is only to check if the
apparent conditions of the site allow the equipment to be delivered.
If the site is not ready, GE can delay the delivery time.
Typical

DELIVERY

2120
[83.5 in]
1114
[43.9 in]
1194
[47 in]
2388
[94 in]
RIGHT SIDE VIEW OF MAGNET
PATH WITH 90 DEGREE TURN
2700
[106.3 in]
SIGNA PIONEER

CRITICAL ITEMS FOR MAGNET DELIVERY

24/7 chilled water and 480v power for shield/cryo cooler
24/7 120v power for the magnet monitor
Phone lines for magnet monitoring and emergency use
Magnet room exhaust fan
Cryogen venting (if roof hatch, completed within 24 hrs)
Magnet anchors installed and tested
This is only a partial list of items required for delivery of the magnet. For a complete checklist refer to the
pre-installation manual referenced on cover sheet.
EQUIPMENT
Replacement XRM gradient coil assembly
on a shipping cradle/cart
The weight bearing structure of the site should support any additional weight of the main replacement parts
occurring during maintenance of the magnet, throughout the whole lifecycle of the MR.
EN-MRI-TYP-SIGNA_PIONEER-WEB.DWG

GRADIENT COIL REPLACEMENT

2536
991
[99.8 in]
[39 in]
DIMENSIONS LxWxH
WEIGHT
kg
mm
in
lbs
Initial gradient coil assembly is shipped installed
991x2536x1499 39x99.84x59 1449
3194
in the magnet. Shipping/installation cart is used to
install replacement coil assembly only.
Rev
A
Date
23/Jul/2018
NOTE
A8 - Delivery
10
/24

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents