Task 10: Control Box Connections
The following instructions illustrate the placement of the
control box onto the operator's platform and the connection
of the associated cables.
1. Align the two pins at the bottom of the control box with
the holes on the operator's platform (Figure 25). Set
control box down on operator's platform.
!
Figure 25. Control Box Mounting
2. Locate the 2-wire female connector plug (Figure 26)
at the control box. Insert this plug into the 2-pin male
receptacle located just underneath the speed control
valve.
Figure 26. Solenoid Valve Plug Connection
PAGE 43 — WRS5200DFPU HYDRAULIC ROLLER SCREED • OPERATION MANUAL — REV. #2 (03/08/18)
ROLLER SCREED ASSEMBLY
3. Locate the 55 ft. (16.76 meters) power cable P/N
46158. Route this cable (Figure 27) from the control
box thru the trusses to the 14-pin receptacle located
on the power unit.
!
14-PIN
RECEPTACLE
Figure 27. Power Cable Connection
NOTICE
The 2-wire female connector plug provides an
electronic signal to the solenoid valve to stop the
hydraulic pressure flow to the drive tubes in the event
the operator leaves the operators seat during operation.
46158