Strike Tube Installation (Middle Section)
The 14ft. (4.25 meters) strike tube section should now be
attached to the matching section of truss (Figure 19). The
following section will illustrate inserting the middle section
strike tube.
1. The first middle bracket should now be installed with
the splined shaft supporting one end of the 14 ft. (4.24
meters) strike tube. The other end of the splined shaft
should be exposed.
2. Insert one end of the 16 ft. (4.87 meters) strike tube
onto the exposed-end of the splined shaft located on
the first middle bracket (Figure 19).
3. Next, insert the other end of the strike tube onto the
splined shaft of the second middle bracket (Figure 19).
PAGE 39 — WRS5200DFPU HYDRAULIC ROLLER SCREED • OPERATION MANUAL — REV. #2 (03/08/18)
Figure 19. Strike Tube Middle Section (16 ft./4.87 meters)
ROLLER SCREED ASSEMBLY