Dell SC4020 Deployment Manual page 62

Storage center
Hide thumbs Also See for SC4020:
Table of Contents

Advertisement

Steps
1.
Connect each server to both FC fabrics.
2.
Connect fault domain 1 (shown in orange) to fabric 1.
Primary port P1 — Storage controller 1: port 1 to FC switch 1
Reserved port R1 — Storage controller 2: port 1 to FC switch 1
3.
Connect fault domain 2 (shown in blue) to fabric 1.
Primary port P2 — Storage controller 2: port 2 to FC switch 1
Reserved port R2 — Storage controller 1: port 2 to FC switch 1
4.
Connect fault domain 3 (shown in gray) to fabric 2.
Primary port P3 — Storage controller 1: port 3 to FC switch 2
Reserved port R3 — Storage controller 2: port 3 to FC switch 2
5.
Connect fault domain 4 (shown in red) to fabric 2.
Primary port P4 — Storage controller 2: port 4 to FC switch 2
Reserved port R4 — Storage controller 1: port 4 to FC switch 2
Example
Figure 49. Storage System in Legacy Mode with Dual 8 Gb Storage Controllers and Two Fibre Channel
Switches
1.
Server 1
3.
FC switch 1 (Fault domain 1)
5.
Storage system
7.
Storage controller 2
Next steps
Install or enable MPIO on the host servers.
NOTE: For the latest best practices, see the Dell Storage Center Best Practices document located
on the Dell TechCenter (http://en.community.dell.com/techcenter/storage/).
62
2.
Server 2
4.
FC switch 2 (Fault domain 2)
6.
Storage controller 1
Connect the Front-End Cabling