9 Requirements to be met by acceptance inspection
The acceptance inspection of the safety function is ordered by the manufacturer of the machine. The
inspection (acceptance, validation) shall be performed by a properly qualified person.
The result of the inspection is to be documented and must be signed by the inspector. Each safety
function must be documented in detail in this report.
The inspections also include the machine documentation, including its safety functions. The safety func-
tions must be checked particularly during the inspection and documented in the inspection report. Pa-
rameter settings shall be attached to the report. Further documents shall be added, as required, de-
pending on the machine.
Depending on the result of the risk analysis, inspection reports of the regular inspections shall be issued
and signed by the inspector.