Section 3 Starting Up; Factory And Site Acceptance Testing; Commissioning Checklist - ABB REG650 Commissioning Manual

Relion 650 series generator protection
Hide thumbs Also See for REG650:
Table of Contents

Advertisement

1MRK 502 049-UEN A
Section 3
3.1
3.2
Commissioning manual
Starting up

Factory and site acceptance testing

Testing the proper IED operation is carried out at different occasions, for example:
Acceptance testing
Commissioning testing
Maintenance testing
This manual describes the workflow and the steps to carry out the commissioning
testing.
Factory acceptance testing (FAT) is typically done to verify that the IED and its
corresponding configuration meet the requirements of the utility or industry. This test
is the most complex and in depth, as it is done to familiarize the user with a new
product or to verify a new configuration. The complexity of this testing depends on
several factors, such as:
New IED type
New configuration
Modified configuration
Site acceptance testing (SAT or commissioning testing) is typically done to verify that
the installed IED is correctly set and connected to the power system. SAT requires that
the acceptance testing has been performed and that the application configuration is
verified.
Maintenance testing is a periodic verification that the IED is healthy and has correct
settings, depending on changes in the power system. There are also other types of
maintenance testing.

Commissioning checklist

Before starting up commissioning at site, check that the following items are available.
Single line diagram
Protection block diagram
Circuit diagram
Setting list and configuration
RJ-45 Ethernet cable (CAT 5)
Three-phase test kit or other test equipment depending on the complexity of the
configuration and functions to be tested.
Section 3
Starting up
21

Advertisement

Table of Contents
loading

Table of Contents