Installing Optional Circuit Breaker Guard

Procedure
1.
Follow the procedure in Figure 9.
Figure 9:
Installing Optional Circuit Breaker Guard
1. Remove this bracket.

INITIALLY STARTING THE SYSTEM

• Ensure all furnished protective covers are installed.
• If provided, ensure all battery circuit breakers are placed in the ON position.
NOTE!
Circuit breakers are provided with lockout/tagout capability.
• Refer to any Initial Startup procedure in the documentation supplied with the respective power system.
Vertiv
| NetSure Battery Rack System (+24 VDC) Installation Manual (Section 6044) | Rev. E
2. Replace this hardware after
removing existing bracket.
3. Install Circuit Breaker
Guard Bracket using
existing hardware.
Installed View
20