Vertiv 24BA1200-23 Installation Manual page 16

Netsure battery rack system (+24 vdc)
Table of Contents

Advertisement

7.
Connect the cables found in the battery tray to the respective battery terminals, "+" to "+" and "–" to "– ".
Observe correct polarity. Refer to Figure 6 or Figure 7. Torque battery connections to battery
manufacturer's recommendations.
8.
Repeat steps 1 through 7 for any remaining battery trays.
If Battery Trays Are Equipped With Circuit Breakers: To connect the batteries to the Power System,
9.
turn ON the Battery Disconnect circuit breakers located on all battery trays.
Vertiv
| NetSure Battery Rack System (+24 VDC) Installation Manual (Section 6044) | Rev. E
16