INSTALLATION ACCEPTANCE CHECKLIST

Provided below is an Installation Acceptance Checklist. This checklist helps ensure proper installation and
initial operation of the system. As the procedures presented in this document are completed, check the
appropriate box in this list. If the procedure is not required for your installation site, also check the box in this
list to indicate that the procedure was read. When installation is done, ensure that each block in this list has
been checked.
 Relay Rack Mounted to Floor
 Relay Rack Grounding Connection Made
 Battery Disconnect Circuit Breakers (if furnished) External Alarm Connections Made
 Battery Connections to Respective Power System Made
 Batteries Installed
 System Started

MOUNTING THE RELAY RACK

This equipment is intended only for installation in a Restricted Access Location on or above a non-combustible
surface.
The installer should be familiar with the installation requirements and techniques to be used in mounting the
relay rack to the floor.
Refer to Figure 1 or Figure 2 for floor mounting hole dimensions.
Vertiv
| NetSure Battery Rack System (+24 VDC) Installation Manual (Section 6044) | Rev. E
9

Advertisement

Table of Contents
loading

This manual is also suitable for:

24ba1200-19

Table of Contents