Installing Batteries; Observe The Following Admonishment; Battery Manufacturer Information; Installing Batteries Into The Battery Shelves - Vertiv 24BA1200-23 Installation Manual

Netsure battery rack system (+24 vdc)
Table of Contents

Advertisement

INSTALLING BATTERIES

Observe the Following Admonishment

DANGER! Batteries can produce explosive gasses and large amounts of electrical current. Read and
follow the Safety Statement at the beginning of this document before proceeding.

Battery Manufacturer Information

Refer to System Application Guide SAG588810100_SAG588810200 for specifications and manufacturers of the
batteries to be installed in this Battery Rack System.

Installing Batteries into the Battery Shelves

Procedure
1.
If Battery Trays are equipped with Circuit Breakers: Turn OFF the Battery Disconnect circuit
breakers located on all battery trays. Refer to Figure 6 or Figure 7 for locations.
2.
Remove the Battery Retention Bracket as shown in Figure 6 or Figure 7. To do so, remove the four 1/4-
20 x 5/8" bolts and associated washers.
3.
Slide batteries into the tray, with the battery terminals toward the front as shown in Figure 6 or Figure 7.
Slide batteries into the tray as far as they will go.
NOTE!
The Battery Retention Bracket can be oriented two ways to accommodate batteries of different
lengths. A correctly oriented bracket will fit snuggly against the batteries.
Spec No. 588810200 Only: If your batteries require the alternate bracket orientation shown in Detail A
of Figure 7, remove and reinstall the bullet-shaped spacers as shown in Detail A before performing the
next step.
4.
Reinstall the Battery Retention Bracket. Secure with the hardware removed in a previous step. Refer to
Figure 6 or Figure 7 for washer location.
Spec No. 588810200 Only: The spacers on the bracket should separate the batteries from each other.
5.
Connect two links supplied by the battery manufacturer between pairs of battery terminals as shown in
Figure 6 or Figure 7 Use hardware furnished by the battery manufacturer. Torque hardware to battery
manufacturer's recommendations.
6.
Ensure the battery cable ends in all trays are insulated with sleeving before performing the next step.
DANGER! In multiple-tray installations, when batteries in one tray are connected, the battery cables in
all trays will be energized. Remove sleeving from and connect one cable at a time. Do not allow cable
end to contact the battery tray or equipment rack.
ALERT! In the next step, observe correct polarity. Connect only cable labeled "+" to battery terminal
labeled "+". Likewise, connect only cable labeled "–" to battery terminal labeled "–".
Vertiv
| NetSure Battery Rack System (+24 VDC) Installation Manual (Section 6044) | Rev. E
15