Set The Snow-Proof Function; Dismantling The Panel; Explanation Of Valve - Carrier Xpower Series Installation Manual

Full dc inverter xpower vrf outdoor unit
Hide thumbs Also See for Xpower Series:
Table of Contents

Advertisement

4.8 Set the snow-proof function

Applies to snowy areas (see the figure below). Defective
equipment may cause a malfunction. Lift the bracket and
install the snow shed at the air inlet and air outlet.
Snow shed for air inlet
Snow shed for air inlet

4.9 Dismantling the panel

1. Dismantle the front left and right posts: Remove the four screws
from the left and right posts (Fig 4-15). Then rotate the posts, and
lift them by about 2 mm ( Fig 4-16 and Fig 4-17) to remove them.
2. Dismantling the upper panel: Remove the four screws on the left
and right side of the upper panel (Fig 4-18) and then lift it by
about 3 mm to remove it.
A
A
Installation manual
8
Snow shed for air outlet
Fig.4-14
Fig.4-15
A
A
Fig.4-16
A
1:2
(Hooks on the upright post; one
on each of the upper, middle, and
lower position of the upright post)
The figure shown above is for reference only and the actual panel
may be different.

4.10 Explanation of valve

1
Liquid side ball valve
1
Connecting Oil balance
2
Gas side ball valve
3
Needle valve (for pressure tests and adding refrigerant)
4
Note: For a single module, there's no need to connect an oil
balance pipe.
5~10°
Fig.4-17
Fig.4-18
3
4
2
Fig.4-19
pipe(※)