An alternative type of load shedding scheme would be to set all underfrequency stages to about the same
frequency setting but to have different length time delays set on each stage. If after the first stage is shed the
frequency doesn't recover then subsequent stages will shed after longer time delays have elapsed.
Generator
5
1
Figure 2.16-1 Load Shedding Scheme Using Under-Frequency Elements
Page 32 of 48
STAGE 1: Least important
STAGE 2
STAGE 3
STAGE 4
2
6
Essential
Load
Network
Incomer
300/5
5
3
©2017 Siemens Protection Devices Limited
G59
4
2
4