Tests; Inspection; Secondary Injection Tests; Primary Injection Tests - Siemens 7SR12 Argus Manual

Overcurrent relay energy management
Hide thumbs Also See for 7SR12 Argus:
Table of Contents

Advertisement

7SR11 & 7SR12 Commissioning and Maintenance Guide
The currently Active Group and the group currently Viewed are shown at the top of the display in the Settings
display screen. If the View Group is not shown at the top of the display, this indicates that the setting is common
to all groups. CT/VT ratio, I/O mapping and other settings which are directly related to hardware are common to
all groups.
If the relay is allowed to trip during testing then the instruments display will be interrupted and replaced by the
'Trip Alert' screen which displays fault data information. If this normal operation interferes with testing then this
function can be temporarily disabled for the duration of testing by use of the Trip Alert Enabled/Disabled setting in
the System Config Menu.
After applying a settings change to the relay, which may involve a change to the indication and output contacts,
the TEST/RESET key should be pressed to ensure any existing indication and output is correctly cleared.
1.3

Tests

1.3.1

Inspection

Ensure that all connections are tight and correct to the relay wiring diagram and the scheme diagram. Record any
deviations. Check that the relay is correctly programmed and that it is fully inserted into the case. Refer to
'Section 2: Settings and Instruments' for information on programming the relay.
1.3.2

Secondary Injection Tests

Select the required relay configuration and settings for the application.
Isolate the auxiliary D.C. supplies for alarm and tripping from the relay and remove the trip and intertrip links.
Carry out injection tests for each relay function, as described in this document
For all high current tests it must be ensured that the test equipment has the required rating and stability and that
the relay is not stressed beyond its thermal limit.
1.3.3

Primary Injection Tests

Primary injection tests are essential to check the ratio and polarity of the transformers as well as the secondary
wiring.
Note. If the current transformers associated with the protection are located in power transformer bushings it may
not be possible to apply test connections between the current transformer and the power transformer windings.
Primary injection is needed, however, to verify the polarity of the CTs. In these circumstances primary current
must be injected through the associated power transformer winding. It may be necessary to short circuit another
winding in order to allow current to flow. During these primary injection tests the injected current is likely to be
small due to the impedance of the transformer.
1.3.4

Putting into Service

After tests have been performed satisfactorily the relay should be put back into service as follows:-
Remove all test connections.
Replace all secondary circuit fuses and links, or close m.c.b.
Ensure the Protection Healthy LED is on, steady, and that all LED indications are correct. If necessary press
CANCEL until the Relay Identifier screen is displayed, then press TEST/RESET to reset the indication LEDs.
The relay meters should be checked in Instruments Mode with the relay on load.
The relay settings should be downloaded to a computer and a printout of the settings produced. The installed
settings should then be compared against the required settings supplied before testing began. Automated setting
comparison can be carried out by Reydisp using the Compare Settings Groups function in the Edit menu. Any
modified settings will be clearly highlighted.
©2017 Siemens Protection Devices Limited
Chapter 6 Page 8 of 72

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

7sr11 argus

Table of Contents