Installation Procedure:
• Refer to "Attachment Installation" on page 5-10.
Operation:
• Raise or lower boom to appropriate height for loading material from stockpile.
• Align telehandler with face of stockpile and drive slowly and smoothly into pile to load
bucket.
• Tilt bucket up far enough to retain load and back away from pile.
• Travel in accordance with requirements set forth in
Section 1- General Safety Practices.
• Tilt bucket down to dump load.
Equipment Damage Precautions:
• Except for lifting or dumping a load, the boom must be fully retracted for all bucket
operations.
• Do not corner-load bucket. Distribute material evenly within the bucket. Bucket
capacity charts are for evenly distributed loads only.
• Do not use bucket as a lever to pry material. Excessive prying forces could damage
bucket or machine structure.
• Do not attempt to load material which is hard or frozen. This could cause severe
damage to quick coupler or machine structure.
• Do not use bucket for "back dragging." This could cause severe damage to quick
coupler and retraction cables/chains.
31211018
Section 5- Attachments
5-35

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Skytrak 8042Skytrak 6042Skytrak 10042Skytrak 10054

Table of Contents