Installation and commissioning flowchart

Identify the frame size of your drive: A, B, C or D.
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection, compatibility
of the motor, motor connection, and other technical
data.
Select the cables.
Unpack and check the units.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
Check the installation site.
Install the drive in a cabinet.
Route the cables.
Check the insulation of the supply cable, the motor
and the motor cable, and the resistor cable (if
present).
If the drive is about to be connected to an IT
(ungrounded) system, disconnect the internal
varistors and EMC filters. Also note that using an
EMC filter is not allowed in an IT (ungrounded]
system.
Task
See
Drive designation label or
Ratings
(page 77)
Planning the cabinet assembly
Planning the electrical installation
Technical data
(page 77)
Option manual (if optional equipment is
included)
Mechanical
installation:
Contents of the
package
(page 33)
If the converter has been non-operational for
more than one year, the converter DC link
capacitors need to be reformed. Ask ABB for
more information.
Mechanical installation: Before installation
(page 35)
Technical data
(page 77)
Mechanical
installation:
Installation procedure
(page 36)
Planning the electrical
installation:
cables
(page 46)
Electrical
installation:
Checking the insulation of
the assembly
(page 51)
Safety
instructions:
Installation and
maintenance work
(page 6)
Electrical
installation:
Power cable connection
(page 52)
17
Technical data:
(page 27)
(page 39)
Routing the
About this manual

Advertisement

Table of Contents
loading

Table of Contents