3 Planning instructions for isolating systems
Minimization of the step
response time
Standard applications
12
8
6
4
2
0
5
DN50
6
(1 mm)
7
500 mbar
Fig. 8: Typical step response times (T90) in s/m for different filling oils depend-
ing on the measuring cell and capillary inner diameter. Ambient temperature =
20 °C
1
Silicone oil
2
High temperature oil
3
Med. white oil
4
Inert oil
5
Nominal width
6 Capillary inner diameter
7
Measuring cell
100 %
90 %
Fig. 9: Presentation of the step response time (T90)
1
Pressure jump
2
Output signal
For minimisation of the step response time, you have to following
options:
Bigger capillary inner diameter
Shorter capillaries
Filling oil with lowest viscosity
3.4

Installation position

When the pressure transmitter is mounted above the lower chemical
seal, the max. height difference H1 according to the following illustra-
DN80
DN50
(2 mm)
(1 mm)
3 bar
1
2
T90%
Chemical seal CSB • for VEGADIF 65
1
2
3
4
DN80
(2 mm)
t

Advertisement

Table of Contents
loading

Table of Contents