POST INSTALLATION CHECKLIST

After the station equipment has been mechanically installed and all electrical connections have been made, power
may now be applied and the station checked for proper operation.

Applying Power

Changing Fuse
CAUTION
68P81096E37-N
06/28/05
Before applying power to the station, make sure all boards are securely
seated in the appropriate connectors on the backplane and that all rf cables
are securely connected.
Turn ON the circuit breaker controlling the ac outlet that is supplying
power to the station Power Supply Module, or switch on the DC-supply
to a station with a DC-only Power Supply Module.
To replace the station fuse:
1.
Turn off station power at source (e.g., ac breaker).
2.
Remove fuse cover plate located on the backplane shield by unscrew-
ing one M4 screw.
3.
Pull defective fuse carefully with small needle nose pliers.
4.
Replace new fuse (part # 6583049X16) carefully with small needle
nose pliers.
For continued protection of the station against risk of fire, replace
!
the fuse only with the same type and rating of fuse.
5.
Restore power to the station.