The figure below shows two methods for connecting CTs to the PQMII for a 3-wire system.
The top drawing shows the standard wiring configuration using three CTs. An alternate
wiring configuration uses only two CTs. With the two CT method, the third phase is
measured by connecting the commons from phase A and C to the phase B input on the
PQMII. This causes the phase A and phase C current to flow through the PQMII's phase B CT
in the opposite direction, producing a current equal to the actual phase B current.
Ia + Ib + Ic = 0 for a three wire system.
Ib = – (Ia + Ic)
For the CT connections above, the
PHASE CT WIRING
PHASE CT PRIMARY
FIGURE 2–9: Alternate CT Connections for 3-wire System
S2 SYSTEM SETUP
CURRENT/VOLTAGE CONFIGURATION
setpoint must be set to PHASE A, B, AND C.
PQMII POWER QUALITY METER – INSTRUCTION MANUAL
CHAPTER 2: INSTALLATION

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Pqm ii

Table of Contents