Installation; Location; Mains Power Supply; Recommended Fuse Sizes And Minimum Cable Area - ESAB Buddy Arc 200 Instruction Manual

Table of Contents

Advertisement

GB
Duty cycle
The duty cycle refers to the time as a percentage of a ten-minute period that you can weld or cut at
a certain load without overloading. The duty cycle is valid for 40° C.
Enclosure class
The IP code indicates the enclosure class, i. e. the degree of protection against penetration by solid
objects or water. Equipment marked IP23 is designed for indoor and outdoor use.
Application class
The symbol
indicates that the power source is designed for use in areas with increased
electrical hazard.
4

INSTALLATION

The installation must be carried out by a professional.
4.1

Location

Position the power source such that its cooling air inlets and outlets are not
obstructed.
4.2

Mains power supply

Make sure that the welding power source is connected to the
correct supply voltage and that it is protected by the correct
fuse rating. The outlet shall have a protective earth
connection.
4.2.1

Recommended fuse sizes and minimum cable area

Mains voltage
Mains cable area mm
Phase current I
(TIG)
1eff
Phase current I
(MMA)
1eff
NOTE!
Use the power source in accordance with the relevant national regulations.
bh40d1e
Rating plate with supply connection data
2
Arc 180
230V 1∼ $10%, 50/60 Hz
3 G 2.5
14.7 A
19.7 A
- 7 -
Arc 200
3 G 2.5
16.6 A
24.1 A
© ESAB AB2011