Lippe Lift T80 Assembly Manual page 11

Inclined stair lift - chairlift

Advertisement

8
The rails should be connected with the potential equalization cable which is laid on site (inner
construction: min. Cu 6mm², outer composition: min. Cu 10mm², or according to national
directives).
9.)
The arrangement of the external control device must correspond to the requirements of the
intended user, whether he sits, stands or is in a wheel chair. The height of the external control
device should be 800mm to 1100mm away from the floor. The external control device should be
mounted so that if possible the entire track can be viewed from the respective control center.
In the case of external control devices which are connected among themselves, the cable should be
placed in a cable channel of empty pipe.
10.) Connect plus and minus lines of the loading devices with the loading stations (use crush hoods,
then shrink the heat shrink tube by means of a hot air blower). Connect loading device to the house
network. Subsequently check the function (function check is only possible if the load carrying
equipment is standing with its loading contacts in the loading station). The loading device should
be attached so that the user can see it easily.
Installation manual Konstanz DC
Potential
equalization..............
11/25
Version 8.0
Last update: 2/15/10