COMMISSIONING THE FIRE - Page 11
Check the electricity supply to the fire unit by switching on
the illumination bulbs to the coal bed. If the bulbs light,
switch off and continue with commissioning the fire. If the
bulbs do not light, isolate the electricity supply and perform
preliminary electrical system checks before proceeding i.e.
earth continuity, polarity, resistance to earth etc.
Isolate the electricity supply.
Remove the electrical cover on the right hand side of the
chassis as shown, by removing the fixing screw.
Release the pressure test point sealing screw and connect a
pressure gauge in position.
Reconnect the electricity supply.
Push in the control knob, turn to the IGNITION position (
)
and hold in. Sparking will commence at the ignition electrode
and the pilot will ignite.
Continue to hold the control knob in for a further 15 seconds
then release. The sparking will stop and the pilot will stay
alight. If the pilot does not stay alight, repeat the process
after waiting for 3 minutes. (If the pilot still fails to remain
alight, refer to the fault finding chart).