Connections

Connection checklist
Table 65
Connections checklist
Have you:
Obtained a serial cable (DTE-DTE null modem cable) to connect the server to a
maintenance terminal?
Obtained the NTAK19EC cable (if you are connecting a Nortel CP PM server)? This
cable adapts the 50-pin MDF connector on the back of the shelf of the Media Gateway,
Universal Equipment Module, or 11C cabinet to a 25-pin DB connector.
Obtained the CAT5 cables (or better) to connect the server to the ELAN and TLAN
subnets?
Connecting a Nortel CP PM Signaling Server
Communication Server 1000M and Meridian 1
WARNING
Do not modify or use a supplied AC power cord if it is not
the correct type required for the host region.
Nortel CP PM servers are powered through the backplane of the Media
Gateway, Universal Equipment Module or 11C cabinet into which they
are installed and thus require no power cord.
Before connecting a Signaling Server, ensure that you have the following
materials on-hand.
This section contains instructions for connecting the NTDW61BAE5 CP PM
Signaling Server to the ELAN and TLAN subnets of a CS 1000E and
Installing a Signaling Server
IMPORTANT!
Large System Installation and Commissioning
Page 389 of 456

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Meridian 1

Table of Contents