Connecting The Clock Controller Cables - Nortel 1000M Installation And Commissioning Manual

Nortel networks communication server large system installation and commissioning
Hide thumbs Also See for 1000M:
Table of Contents

Advertisement

Connecting the Clock Controller cables

Communication Server 1000M and Meridian 1
Cabling Common Equipment in a Multi Group system
Two Clock Controller cards are required in each system. These cards
synchronize Large System functions. Figure 100 on
Clock Controllers installed in a two-column system.
The Clock Controllers Cards must be installed as directed in the following
three rules.
1
Two Clock Controller cards must be installed in each system. The Clocks
must be connected to each other and to the FIJI cards in Network
Group 0.
2
One Clock Controller must be installed in Network Shelf 0, slot 13. A
second Clock Controller must be installed in Network Shelf 1, slot 13.
3
Clock Controllers should be installed in different Network groups if
possible.
The Clock Controller cannot be installed in the Core/Net
shelf.
IMPORTANT!
Large System Installation and Commissioning
Page 235 of 456
page 236
shows the two

Hide quick links: