System Options - Nortel 1000M Installation And Commissioning Manual

Nortel networks communication server large system installation and commissioning
Hide thumbs Also See for 1000M:
Table of Contents

Advertisement

System options

Meridian 1 PBX 61C and CS 1000M SG
Communication Server 1000M and Meridian 1
The procedures in this document apply to the following system options:
Meridian 1 PBX 61C: dual CPU, full network group
Meridian 1 PBX 81C: dual CPU, multiple network groups
CS 1000M SG: a Meridian 1 PBX 61C system upgraded to include a
Signaling Server (see note below)
CS 1000M MG: a Meridian 1 PBX 81C system upgraded to include a
Signaling Server (see note below)
Note: For information about Signaling Server installation and
configuration, see Signaling Server: Installation and Commissioning
(NN43001-312).
All system options are available in both AC- and DC-powered versions.
System architecture and module types are described in Communication
Server 1000M and Meridian 1: Large System Overview (NN43021-110).
The components of AC-powered systems, DC-powered systems, and reserve
power options for both are described in this document.
These systems feature a dual Pentium Processor with standby processing
capability, fully redundant memory, and a full network group. Two Core/Net
modules and one IPE module are the minimum installation requirements.
Additional IPE modules and application modules can be used. The modules
are stacked (see Figure 5 on
on
page
46).
Preparing for installation
page
46) or installed side-by-side (see Figure 6
Large System Installation and Commissioning
Page 45 of 456