5.3

Starting

Procedure for controller as shown
Step
-
-
-
-
-
-
5.4

During operation

Description for controller as shown
86
Action
At least 10 minutes before starting, the main supply to the dryer must be switched on to
initialize the controller and flow switch.
Close the dryer by-pass valve, if installed.
Press start button (14).
Open the dryer air inlet valve (customer's installation).
Approx. 5 minutes later, open the dryer air outlet valve (customer's installation).
Approx. 10 minutes later, the nominal dew-point will be reached.