Commissioning, inspection, maintenance
Further details regarding the individual steps
Venting the boiler
Venting the heating system
1. Close the gas shut-off valve and
switch ON the control unit.
10
(cont.)
1. Close the shut-off valves on the
heating water side.
2. Connect the drain hose on valve
A with a drain.
3. Open valve A and the fill valve in
the heating return and vent using
mains pressure (flush) until no
more air noise can be heard.
4. Close valve A and the fill valve in
the heating return, and open the
shut-off valves on the heating
water side.
2. Activate the venting program via
coding "2F:1".
Note
To call up coding level 1 and for
setting the coding address, see
page 46.
For function and sequence of the
venting program, see page 109.
Whilst the venting program is run-
ning, the display shows "EL"
(Vitotronic 100) or "Entlüftung"
(venting) (Vitotronic 200).