Installing Xenpak Modules

If you are installing an OS8-10GNI-UR1, you must install
Xenpaks (10 Gigabit Ethernet modules) as required. These
Xenpaks are packaged separately.
Xenpak Module
To install a Xenpak follow the steps below.
1
Be sure you have eliminated ESD by using the
provided grounding wrist strap. Refer to
Grounding Wrist Strap and Chassis Grounding Lug" on
page 12
for more information.
2
Remove the blank slot cover plate from the OS8-
10GNI-UR1's front face and set the cover plate and
screws aside.
March 2005
"Using the
3
Align the groove on the XENPAK module with the
guide rails on the OS8-10GNI-UR1's circuit board as
shown below:
10GNI Module
T
X
R
X
Xenpak Slot
Xenpak Module
T
X
R
X
4
Holding the Xenpak by its sides, carefully slide it into
the desired Xenpak slot.
Caution. The Xenpak should slide in easily. Do not force
it into the slot. If any resistance is encountered, ensure the
Xenpak is aligned properly. Forcing the Xenpak into the
slot can damage the unit, as well as components on your
module.